Question: Items: and On Hand Inventory: S: 20 T: 20 U: 30 V: 20 W:25 X: 25 Y: 60 Z: 40 Find S-Z. The demand for

Items: and On Hand Inventory:
S: 20
T: 20
U: 30
V: 20
W:25
X: 25
Y: 60
Z: 40
Find S-Z.
The demand for subassembly S is 80 units in week 7 . Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 week to make X,2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers)Step by Step Solution