Question: j Construct an AON project network for the following set of activities. Can you find the critical path? (options) 2->5->8 1->4->8 1->3->7 1->3->6->8 begin{tabular}{ccc} hline

j Construct an AON project network for thej

Construct an AON project network for the following set of activities.

Can you find the critical path?

(options)

2->5->8

1->4->8

1->3->7

1->3->6->8

\begin{tabular}{ccc} \hline Activity & Activity Predecessor & Time (months) \\ \hline 1 & & 4 \\ 2 & & 7 \\ 3 & 1 & 8 \\ 4 & 1 & 3 \\ 5 & 2 & 9 \\ 6 & 3 & 5 \\ 7 & 3 & 2 \\ 8 & 4,5,6 & 6 \\ 9 & 2 & 5 \\ \hline \end{tabular}