Question: the total time on the critical path is: Construct an AON project network for the following set of activities. Analyze the project network, answer the

the total time on the critical path is: Construct
the total time on the critical path is:
Construct an AON project network for the following set of activities. Analyze the project network, answer the following questions. Activity Activity Predecessor Time (months) 1 2 3 4 3 1 2 3 4 7 8 3 9 5 2 6 S 7 8 4,5,6 2 9 Which of the following is a critical path? O 2->5->8 O 1->4->8 O 1->3->7 O 1->3->6->8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!