Question: James calculated the slack for a network activity diagram and derived the following slack variables: A=0.0,B=0.5,C=0.0,D=0.0,E=2.0,F=1.0,G=0.0,H=3.0,1=0.0,J=0.7 and K=0.0 The critical path of this project is

James calculated the slack for a network activity
James calculated the slack for a network activity diagram and derived the following slack variables: A=0.0,B=0.5,C=0.0,D=0.0,E=2.0,F=1.0,G=0.0,H=3.0,1=0.0,J=0.7 and K=0.0 The critical path of this project is closest to: a. A, ,D,G,J,K b. A,C,D,G,L,K c. A,B,G,1,J,K d. A, B, D, G, I, K