Question: Jane produces custom greeting cards using six distinct work elements. She would like to produce 6 cards in each 8 -hour card-making session. The figure

Jane produces custom greeting cards using six distinct work elements. She would like to produce 6 cards in each 8 -hour card-making session. The figure to the right details each work element and its associated durations in minutes as well as their precedence relationships. What is the theoretical minimum number of workstations to meet the demand? (Enter your response as an integer.) Jane produces custom greeting cards using six distinct work elements. She would like to produce 6 cards in each 8 -hour card-making session. The figure to the right details each work element and its associated durations in minutes as well as their precedence relationships. What is the theoretical minimum number of workstations to meet the demand? (Enter your response as an integer.)