Question: Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards in each 8-hour card-making session. Figure details each

Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards in each 8-hour card-making session. Figure details each work element and its associated durations in minutes as well as their precedence relationships.

a. What cycle time is required to satisfy the required output rate?

b. What is the theoretical minimum number of workstations required?

c. If lane identifies a five-station solution, what is the associated efficiency and balance delay?

Jane produces custom greeting cards using six distinct work elem


d. If the cycle time increased by 100 percent, would the theoretical minimum number of workstations also increase by 100 percent?

15 10 6 10 0

Step by Step Solution

3.50 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Janes Custom Cards a Output rate equals 10 8 hours which is 125 per hour Cycle time 1 125 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

227-B-M-L-S-C-M (937).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!