Question: Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards in each 8-hour card-making session. Figure details each
Jane produces custom greeting cards using six distinct work elements. She would like to produce 10 cards in each 8-hour card-making session. Figure details each work element and its associated durations in minutes as well as their precedence relationships.
a. What cycle time is required to satisfy the required output rate?
b. What is the theoretical minimum number of workstations required?
c. If lane identifies a five-station solution, what is the associated efficiency and balance delay?
.png)
d. If the cycle time increased by 100 percent, would the theoretical minimum number of workstations also increase by 100 percent?
15 10 6 10 0
Step by Step Solution
3.50 Rating (170 Votes )
There are 3 Steps involved in it
Janes Custom Cards a Output rate equals 10 8 hours which is 125 per hour Cycle time 1 125 ... View full answer