Question: Jim Gilbert would like to determine the critical path for the entire wring assembly project as well as the expected completion time for the total
Jim Gilbert would like to determine the critical path for the entire wring assembly project as well as the expected completion time for the total project.
Calculate slack & identify the critical path.
Immediate Activity Completion Predecessors Time (days)
A --- 3
B A 3
C A 2
D B 3
E C 7
F B, C 3
G E, F, D 4