Question: Referring to Solved Problem 3.4, now Jim Gilbert would like to determine the critical path for the entire wing assembly project as well as the
Referring to Solved Problem 3.4, now Jim Gilbert would like to determine the critical path for the entire wing assembly project as well as the expected completion time for the total project. In addition, he would like to determine the earliest and latest start and finish times for all activities.
Data From Problem 3.4
To complete the wing assembly for an experimental aircraft, Jim Gilbert has laid out the seven major activities involved. These activities have been labeled A through G in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. Determine the expected time and variance for each activity.

ACTIVITY a m b IMMEDIATE PREDECESSORS A 1 2 3 B 2 3 4 - C 4 5 9 A D 00 8 9 10 B E 2 ST 5 8 C, D F 4 LO 5 6 D 17 G 1 2 3 E
Step by Step Solution
3.55 Rating (155 Votes )
There are 3 Steps involved in it
The AON network for Gilberts project is shown in Figure 317 Not... View full answer
Get step-by-step solutions from verified subject matter experts
