Job 397 was recently completed. The following data have been recorded on its job cost sheet: Direct
Fantastic news! We've Found the answer you've been seeking!
Question:
Job 397 was recently completed. The following data have been recorded on its job cost sheet:
Direct materials | $ | 48,000 | ||
Direct labor-hours | 690 | DLHs | ||
Direct labor wage rate | $ | 13 | per DLH | |
Number of units completed | 2,500 | units | ||
The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $10 per direct labor-hour.
Required:
Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2 decimal places.)
unit cost
Unit Cost | ________ |