Question: JOB DUE DATE ( HOURS HENCE ) DURATION ( HOURS REQUIRED ) A 2 8 1 5 B 2 6 9 C 1 8 3

JOB
DUE DATE(HOURS HENCE)
DURATION(HOURS REQUIRED)
A
28
15
B
26
9
C
18
3
D
12
7
E
8
6
Part 2
a) Sequence the jobs according to EDD.
According to the EDD rule, the sequence of jobs should be
E, D, C, B, A
.
Part 3
b) What is the average completion(flow) time?
The average completion(flow) time is
20 days (round your response to one decimal place).
Part 4
c) What is the average job lateness?