Question: Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must
Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day.
| JOB | DUE DATE (HOURS HENCE) | DURATION (HOURS REQUIRED) | ||
| A | 16 | 1 |
| |
| B | 24 | 9 |
| |
| C | 34 | 19 |
| |
| D | 14 | 6 |
| |
| E | 8 | 5 |
| |
Part 2
a) Sequence the jobs according to EDD.
According to the EDD rule, the sequence of jobs should be
???
.
Part 3
b) What is the average completion (flow) time?
The average completion (flow) time is
???
days (round your response to one decimal
place).
Part 4
c) What is the average job lateness?
The average job lateness is
???
days (round your response to one decimal
place).
Part 5
d) What is the average number of jobs in the system?
The average number of jobs in the system is
???
jobs (round your response to one decimal
place).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts