Question: Job Order Days Waiting Process Time Due Date Start Finish Flow Time Late Hepner first 7 1 7 2 0 Allison second 6 2 1

Job Order Days Waiting Process Time Due Date Start Finish Flow Time Late
Hepner first 71720
Allison second 6214
Cheng third 51512
Miller fourth 4869
Dickson fifth 31347
Noel sixth 21233
Bahouth seventh 11688
A. If these jobs have already been sequenced what method was used?
[ Select ]
B. Using this sequence Calculate the Average Days Past Due.
[ Select ]
C. Using this sequence Calculate the Average Flow Rate.
[ Select ]