Question: Job Order Days Waiting Process Time Due Date Start Finish Flow Time Late Allison first 6 2 14 Miller second 4 8 69 Noel third
| Job | Order | Days Waiting | Process Time | Due Date | Start | Finish | Flow Time | Late |
| Allison | first | 6 | 2 | 14 | ||||
| Miller | second | 4 | 8 | 69 | ||||
| Noel | third | 2 | 12 | 33 | ||||
| Dickson | fourth | 3 | 13 | 47 | ||||
| Cheng | fifth | 5 | 15 | 12 | ||||
| Bahouth | sixth | 1 | 16 | 88 | ||||
| Hepner | seventh | 7 | 17 | 20 |
A. If these jobs have already been sequenced what method was used?
[ Select ] ["Earliest Due Date (EDD)", "Slack Time Remaining (STR)", "Shortest Processing Time (SPT)", "First-come, First-served (FCFS)"]
B. Using this sequence Calculate the Average Days Past Due.
[ Select ] ["34.4", "24.4", "14.4", "54.4"]
C. Using this sequence Calculate the Average Flow Rate.
[ Select ] ["32.3", "22.3", "12.3", "42.3"]