Question: Job Process Time due A B 50 100 20 80 60 100 160 50 120 75 E Using the sequencing rule data in the table,

Job Process Time due A B 50 100 20 80 60 100 160
Job Process Time due A B 50 100 20 80 60 100 160 50 120 75 E Using the sequencing rule data in the table, what is the critical ratio for Job E? 2.00 1.50 1.60 1.25