Question: Job Processing time ( Days ) Job Due Date ( Days ) A 1 4 2 3 B 1 5 1 8 C 1 3

Job Processing time (Days) Job Due Date (Days)
A 1423
B 1518
C 1317
D 310
E 1018
There are painting jobs awaiting at a paint shop. Their processing times and due dates are shown in the table. The firm wants to determine the sequence of jobs according to longest processing time (LPT). Jobs are assigned a letter in the order day arrived. What is the average number of jobs in the system? Today is day 1 and work begins today.