Question: Five jobs are waiting to be processed. Their processing times and due dates are given below. Job Processing Time (days) Job due date (days) A
Five jobs are waiting to be processed. Their processing times and due dates are given below.
| Job | Processing Time (days) | Job due date (days) |
| A | 4 | 7 |
| B | 7 | 4 |
| C | 8 | 11 |
| D | 3 | 5 |
| E | 5 | 8 |
- Using the shortest processing time rule, in which order should the jobs be processed?
- Using the earliest due date dispatching rule, in which order should the jobs be processed?
- What is the average flow time by using shortest processing time dispatching rule?
- What is the average number of jobs by using shortest processing time dispatching rule?
5. What is the average lateness by using shortest processing time dispatching rule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock