Question: job : v , w , x , y , z processing time : 3, 1, 4 , 2 , 5 due hrs from now

job : v , w , x , y , z
processing time : 3, 1, 4 , 2 , 5
due hrs from now : 5, 1 , 9, 3 , 7
what's the average tardiness using the shortest processing time rule ?