Question: Jobs A , B , and C are in queue at work center 1 0 before being completed on work center 2 0 . The

Jobs A, B, and C are in queue at work center 10 before being completed on work center 20. The following information pertains to the jobs and the work centers: (Job, Process time (day) at WC 10, process time (day) at WC 20, Due Date): (A,5,3,18); (B,3,6,25); and (C,9,5,20). For this problem, there is no move time between two centers. Today is day 1. If the jobs are scheduled by Johnson's rule today, the total manufacturing lead time in day (from day 1 when the first job starts to the day end when the last job is completed) is:
Group of answer choices
23
none of them
22
25
24