Question: Jobs A , B , and C are in queue at work center 1 0 before being completed on work center 2 0 . The
Jobs A B and C are in queue at work center before being completed on work center The following information pertains to the jobs and the work centers: Job Process time day at WC process time day at WC Due Date: A; B; and C For this problem, there is no move time between two centers. Today is day If the jobs are scheduled by Johnson's rule today, the total manufacturing lead time in day from day when the first job starts to the day end when the last job is completed is: