Question: Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20 . The table below pertains

Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20 . The table below pertains to the jobs and the work centers: (Job, Process time (day) at WC 10, process time (day) at WC 20, Due Date, arriving order). Todav is dav 1. If the jobs are scheduled by the earliest due date (EDD) rule, on which date will job c start on WC 20? Hint: you need to first determine the job's operation order by EDD rule. Then in each work center, you need to schedule each job's start date and end date on both WCs. Day 12 Day 11 Day 10 Day 9 None of them