Question: Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20. The following information pertains to
Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20. The following information pertains to the jobs and the work centers. For this problem, there is no move time. Today is day 1. If the jobs are scheduled by the earliest due date, what date the job C will start at work Center 20?
\
A Day 8
B Day 12
C Day 20
D none of the about
In the question, if today is day 1, and if the jobs are scheduled by the earliest due date, which job cannot be completed on time?
A: C
B: A
C None of the about
D: B
\begin{tabular}{llll} Job & \multicolumn{2}{c}{ Process Time } & Due Date \\ & WorkCenter & WorkCenter & \\ & 10 & 20 & 8 \\ A & 4 & 3 & 24 \\ B & 3 & 2 & 18 \\ C & 5 & 3 & 15 \\ D & 2 & 2 & \end{tabular}