Question: Jobs Process I Time (Working Days) Process II Time (Working Days) A 5 2 B 16 15 C 1 1 D 13 11 E 17

Jobs

Process I Time

(Working Days)

Process II Time

(Working Days)

A

5

2

B

16

15

C

1

1

D

13

11

E

17

3

F

18

7

Draw Gantt chart of the optimal order. If there is more than one optimal order, show all Gantt charts.