Question: Jobs Process I Time (Working Days) Process II Time (Working Days) A 5 2 B 16 15 C 1 1 D 13 11 E 17
| Jobs | Process I Time (Working Days) | Process II Time (Working Days) |
| A | 5 | 2 |
| B | 16 | 15 |
| C | 1 | 1 |
| D | 13 | 11 |
| E | 17 | 3 |
| F | 18 | 7 |
ai)Use Johnsons rule to determine the optimal sequence to schedule the jobs. If there is more than one optimal sequence, show them all
aii)Draw Gantt chart of the optimal order. If there is more than one optimal order, show all Gantt charts
aiii)What is the time required for the processes to complete all six jobs?
Step by Step Solution
There are 3 Steps involved in it