Question: Jobs Processing Time Due Date (Days) A 2 2 B 5 6 C 6 10 D 3 4 E 4 8 Using EDD priority rule,

Jobs Processing Time Due Date (Days)
A 2 2
B

5

6
C 6 10
D 3 4
E 4 8

Using EDD priority rule, what is the average WIP at the centre? Calculate the number of jobs to 2 decimal places (2 marks)