Question: Joe is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of

Joe is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following tools is he using?

Select one:

a.

Template

b.

Analogous estimating

c.

Parametric estimating

d.

Learning curve