Question: Joe used a project management software package for a PERT project. It provided the following results: Expected project completion time = 22 days Variance of
Joe used a project management software package for a PERT project. It provided the following results:
Expected project completion time = 22 days
Variance of project completion time = 2.77 days (***Note: this is a variance, NOT a standard deviation***)
What is the probability of completing the project in 22 days or less?
| 0.2743 | ||
| 0.5000 | ||
| 0.7743 | ||
| 0.2257 |