Question: John Dow has constructed the incomplete time-phased MPS record shown. On hand = 130 Week 1 2 3 4 5 6 7 8 Forecast 40
John Dow has constructed the incomplete time-phased MPS record shown. On hand = 130
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Forecast | 40 | 40 | 40 | 40 | 40 | 40 | 30 | 30 |
| Orders | 36 | 40 | 25 | 50 | 25 | 30 | 20 | 10 |
| Available |
|
|
|
|
|
|
|
|
| Available to promise |
|
|
|
|
|
|
|
|
| MPS |
|
| 100 |
|
| 100 |
|
|
The available to promise in week 1 is:
The available to promise in week 3 is:
The available to promise in week 6 is:
The projected available balance in week 3 is:
The projected available balance in week 6 is:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
