Question: John is a project manager on a bridge construction project. John calls a meeting to gain approval from the customer before the contractor orders materials

John is a project manager on a bridge construction project. John calls a meeting to gain approval from the customer before the contractor orders materials that have an extended delivery time (so as not to delay the project schedule).
The above is an example of a
problem-solving meeting
preliminary design review meeting
final design review meeting
status review meeting
material review meeting