Question: John is a project manager on a bridge construction project. John calls a meeting to gain approval from the customer before the contractor orders materials
John is a project manager on a bridge construction project. John calls a meeting to gain approval from the customer before the contractor orders materials that have an extended delivery time so as not to delay the project schedule
The above is an example of a
problemsolving meeting
preliminary design review meeting
final design review meeting
status review meeting
material review meeting