Question: John is in the process of preparing the project performance report for the team meeting. He is expecting many questions from his stakeholders on the

John is in the process of preparing the project performance report for the team meeting. He is expecting many questions from his stakeholders on the budget and schedule. The project was scheduled to be complete in 14 months. He calculates the following values; Earned Value (EV)= $ 12, Planned Value (PV)= $ 10, Actual cost (AC)= $15. What is the new time for completion (ETC) for the project if the work is performed at the budgeted rate?
Give your answer to 2 decimal places