Question: John works as a project manager for uCertify Inc. He's working on a project and finds that there are multiple risks that will affect several
John works as a project manager for uCertify Inc. He's working on a project and finds that there are multiple risks that will affect several stakeholder requirements. Which of the following will he use to share all information on the project risks to stakeholders? option A Risk management plan option B Communications management plan option C Procurement management plan option D Stakeholder management plan