Question: Johnsons' Rule in Sequencing below will result in: A, B,C,E,D To do ---> Calculate completion time? JOB Process 1 A 4 B 10 D
Johnsons' Rule in Sequencing below will result in: A, B,C,E,D To do ---> Calculate completion time? JOB Process 1 A 4 B 10 D E 8 6 8 Process 2 6 5 4 7 9
Step by Step Solution
There are 3 Steps involved in it
Johnsons Rule is a sequencing technique used to minimize the total completion time of a set of jobs ... View full answer