Question: Johnson's Rule results in an optimal sequence when there are only two serial processes. all jobs follow the same sequence through the processes. the objective

Johnson's Rule results in an optimal sequence when
there are only two serial processes.
all jobs follow the same sequence through the processes.
the objective is to minimize makespan.
all of the above
 Johnson's Rule results in an optimal sequence when there are only