Question: Just answer D please 4. A project has the following activities: begin{tabular}{|c|c|c|c|c|c|} hline & Immediate & Normal & Normal & Crash & Crash hline

Just answer D please
Just answer D please 4. A project has the following activities: \begin{tabular}{|c|c|c|c|c|c|}

4. A project has the following activities: \begin{tabular}{|c|c|c|c|c|c|} \hline & Immediate & Normal & Normal & Crash & Crash \\ \hline tivity & Predecessors & (weeks) & (s) & (weeks) & (8) \\ \hline A & none & 4 & 3,000 & 83 & 5,000 \\ \hline B & A & 9 & 5,000 & 7 & 8,000 \\ \hline c & A & 4 & 7,000 & 4 & 7,000 \\ \hline D & B, C & 6 & 6,000 & 4 & 8,000 \\ \hline E & C & 8 & 4,000 & 6 & 8,000 \\ \hline F & D & 3 & 4,000 & 2 & 9,000 \\ \hline G & E,F & 4 & 2,000 & 2 &, 000 \\ \hline \end{tabular} a) Draw the network diagram based on normal time. b) What are potential paths (connected paths) and corresponding durations? c) What is the expected project completion time based on normal time? - The expected project completion time is 26 weeks. d) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!