Question: Keep in mind that A can be crashed 2 days, from 5 down to 3 days, etc. - How much total slack is associated with

Keep in mind that A can be crashed 2 days, from 5

Keep in mind that A can be crashed 2 days, from 5 down to 3 days, etc.

- How much total slack is associated with task E assuming no crashing?

- What is the slack for task A assuming no crashing?

- Which task will you crash first? then second? then third?

- By how many days did you crash task D?

- How much slack is associated with task B assuming no crashing?

Please & thank you. I look forward to giving a positive rating!

-

For each task determine it ES, EF, LS, LF and slack. Determine the critical path. Find the best crashing strategy considering that you have $8.500 for the budget. FTASK crash cost minimum crashed Normal uncrashed predecessor per day Duration Duration LA $1000 3 5 B $500 2 4 $ 600 B 12 Ar A $200 6 , E $800 15 B, C DE A Hotdot 3 10 13 $700

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!