Question: Task Crash cost/day Minimum crashed duration Normal un-crashed Duration Predecessor(s) op $500 $200 $1,000 $400 $900 $700 09 BC B,C DE Note from above that

Task Crash cost/day Minimum crashed duration
Task Crash cost/day Minimum crashed duration Normal un-crashed Duration Predecessor(s) op $500 $200 $1,000 $400 $900 $700 09 BC B,C DE Note from above that A can be crashed 2 days, from 5 down to 3 days, etc Use the following table to create your crashed solution CRASH CRASH PATHS LENGTH (Days) Day(s) Day(s) CRASH Day(s) BUDGET SPENT BUDGET LEFT 0 $9.900 What is the length of the critical path assuming no crashing