Question: Key information on a product new release project is captured in the hereunder table, including activities, predecessors, expected durations and variances ( in days )

Key information on a product new release project is captured in the hereunder table, including activities, predecessors, expected durations and variances (in days).
What is the critical path of the project? Please include the project network, either in Microsoft Project, or manually if neatly drawn. In either case, make sure you clearly show the critical path.
What is the probability of completing the project in 20 days? 30 days?
\table[[ID,Description,Predecessor,te,Variance],[1,pilot production,none,8,4],[2,select channels of distribution,none,5,5],[3,develop marketing program,none,4,1],[4,test market,1,4,2],[5,Patent,1,7,5],[6,full production,4,10,9],[7,ad promotion,2,3,3,2],[8,release,5,6,7,2,1]]
 Key information on a product new release project is captured in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!