Question: Khaki Ltd has been asked to refit a machine for a customer. Skilled labour costing 2 0 per hour will be required for the refit.

Khaki Ltd has been asked to refit a machine for a customer. Skilled labour costing 20 per hour will be required for the refit. The workers will have to be taken off the production of Machine XYZ for sale for a total of 520 hours. Machine XYZ are sold for 720 each and take 26 hours of skilled labour. The material cost of each Machine XYZ is 110. What is the relevant cost when assessing the viability of the refit contract?