Question: Knowing that the Cost Performance Index represents value earned in the project - the amount of completed work for every unit of cost spent. In
Knowing that the Cost Performance Index represents value earned in the project - the amount of completed work for every unit of cost spent. In your own words, explain why a CPI over 1 represents under budget. Use the fact that $1.00 has been spent and your CPI is 1.23. What does "1.23" mean?
Step by Step Solution
There are 3 Steps involved in it