Kumar adds a "finish no later than" date constraint to his schedule. Two activities now show that they will finish later than the project complete milestone. How can he address this negative slack?
Select an answer:
- Change the critical threshold setting to the lowest total slack value in the schedule.
- Rework the dates for all the activities on the critical path in the schedule.
- Redefine which tasks in the schedule are on the critical path and which ones are not.