Question: L-4-L 1 2 3 4 5 6 7 8 9 10 Gross requirements 70 0 90 0 100 70 70 0 45 30 Scheduled receipts

L-4-L 1 2 3 4 5 6 7 8 9 10 Gross requirements 70
L-4-L
1 2 3 4 5 6 7 8 9 10
Gross requirements 70 0 90 0 100 70 70 0 45 30
Scheduled receipts 20 20 20
Projected on hand 35
Net requirements
Planned order receipts
Planned order releases 0
Lead Time 2 Weeks
Holding Cost 3USD per unit per week
Setup Cost 130USD
L-4-L
EOQ
Fill the MRP sheet using both techniques
calculate total cost of both techniques
select optimal option