Question: LA County and Thompson Construction create a contract that includes several complex calculations on which the charges are based. Thompsons engineer, Anthony, performed the calculations.
LA County and Thompson Construction create a contract that includes several complex calculations on which the charges are based. Thompsons engineer, Anthony, performed the calculations. After the proposal was accepted by L.A, Anthony discovered errors resulting on wrong charges. LA does not agree to a correction. Thompson should
-
Do nothing and must perform as agreed.
-
Ask the court to cancel the contract on the basis of fraud.
-
Ask the court to reform the contract on the basis of mistake.
-
Ask the court to enjoin the contract
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts