Question: Last 3 drop downs the options are: Arrival Order, SPT sequence, EDD sequence Eight jobs have arrived in the following order: Find and compare the

Last 3 drop downs the options are: Arrival Order, SPT sequence, EDD sequence
Eight jobs have arrived in the following order: Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. a. Process in the order they have arrived b. Shortest processing time The SPT sequence is c. Earliest due date The EDD sequence is The has the smallest average flow time. The has the smallest average lateness. The has the smallest average tardinessStep by Step Solution