Question: Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 12 kanbans

Lead time for computers is 5 days with daily
Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 12 kanbans how many computers should each one hold

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!