Question: Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants

Question 26 3 points Lead time for computers is 5
Question 26 3 points Lead time for computers is 5 days with daily demand of 25 and safety stock of 5 computers. If management wants to use 15 kanbans how many computers should each one hold? lead time daily demand safety stock number of kanbans Excel Access 5 days 25 units per day 5 units 15