Question: Lead time for computers is 5 days with daily demand of 2 5 computers and a safety stock of 3 days. Each kanban holds 2

Lead time for computers is 5 days with daily demand of 25 computers and a safety stock of 3 days. Each kanban holds 20 computers. What is the correct number of kanbans?
Group of answer choices
8
5
7
10
4.5