Question: LEAN PRODUCTION - Stability 5S TPM Production cell with the following conditions Working time: 3 shifts/day, 5 days/week Shift hours: 6:00 14:00, 14:00 22:00, 22:00
LEAN PRODUCTION - Stability 5S TPM
Production cell with the following conditions
Working time: 3 shifts/day, 5 days/week
Shift hours: 6:00 14:00, 14:00 22:00, 22:00 6:00
Planning related stops (no production):
Breaks: 30 minutes each shift
Meetings: Every Thursday 13:30 14:00
Preventive maintenance: daily during shift exchange at 6:00-6:15, 14:00 14:15, 22:00-22:15
Production: cycle time 9 minutes/item
True outcome during one week:
Breakdowns: Mon: 6:30-10:00; Tue: 9:00 10:12, Wed: 20:30 -21:48; Fri: 14:30 17:18
There are 553 items produced of which 8 were scrap
Calculate OEE, MTBF, MTTR for that week