Question: Learning Activity 5 Based on the following table, determine the design capacity, utilization, and efficiency of production 6 2 shifts and 8 hours Number of

Learning Activity 5 Based on the following table, determine the design capacity, utilization, and efficiency of production 6 2 shifts and 8 hours Number of working days in week Number of working shifts and hours in a day Actual output Effective capacity Design capacity 123.000 last week 150.000 3 per hour