Question: Learning Curve problem Show Process 1) A new employee at the GGA Co. took 186 and 140 minutes to assemble the fourth and eight assemblies,
Learning Curve problem Show Process
1) A new employee at the GGA Co. took 186 and 140 minutes to assemble the fourth and eight assemblies, respectively. The standard time for assembling this product is 100 minutes.
a) Calculate this workers learning curve.
b) How many assemblies does it take the worker to achieve the standard time?