Question: Legend: Planned Task Task has been completed (as of week 3 ) Tasks whose planned status does not its match actual status Tasks actual status

Legend: Planned Task Task has been completed (as of week 3 ) Tasks whose planned status does not its match actual status Tasks actual status New projected completion Project's baselned Gantt chart as of the end of week three (3) Question 1: 50/50 Rule Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value table for tasks A,C,F,J,KM and O